Roywood

Overview

  • Ward: Don Valley East (Ward 34)
  • Activity: Overhead Rebuild
  • Timeline: August - December 2013
  • Status: Completed

Toronto Hydro - Electric System Limited (“Toronto Hydro”) is planning to rebuild the aging overhead electrical system in the community. The rebuild includes relocating hydro poles and associated equipment within the City of Toronto’s public property allowance in front of or adjacent to the lot.

Once construction begins, Toronto Hydro crews and contractors will take extra care and precaution to minimize inconveniences. Please be advised that as a result of the project, Toronto Hydro’s contractor may be trimming a number of the overgrown trees on the public road allowance in order to accommodate new hydro infrastructure. Upon project completion, affected areas will be restored to pre-construction conditions.

Project update icon Updates

  • Week of January 13, 2014

    Toronto Hydro is pleased to report that the electrical phase of this project is underway. Our crews and contractors will be working in the neighbourhood from February until July 2014.

Photos

Poll

After visiting this site, how satisfied are you with the quality of information displayed?